Vattenfall will kick off construction next month at the £60m Clashindarroch wind farm near Huntly in Aberdeenshire.
The company expects to wrap up work on the 18-turbine development in late 2014 with full power due in winter or spring 2015.
Repower has been lined up to provide its MM-series 2.05MW hardware for the 36.9MW project, as first reported exclusively on 9 May in subscriber-only newsletter reNews.
Delivery of wind turbines is scheduled for summer 2014, following construction of roads this year and foundation pours in spring 2014.
RJ McLeod has been lined up to tackle civil engineering. The company has an established track record with renewable energy projects.
Repower has been lined up to provide its MM-series 2.05MW hardware for the 36.9MW project, as first reported exclusively on 9 May in subscriber-only newsletter reNews.
Delivery of wind turbines is scheduled for summer 2014, following construction of roads this year and foundation pours in spring 2014.
RJ McLeod has been lined up to tackle civil engineering. The company has an established track record with renewable energy projects.